|
Mapleton Expeditionary School of the Arts (MESA) and Mapleton Early College (MEC) Bond Project Information
Progress Updates
Week ending April 1, 2012
Work in Progress:
Sitework:
- Grading for East basketball court in progress at time of site walk. Concrete at East side of Clayton placed today, grading in progress.
MEC:
- 1st Floor drywall installation nearly complete, drywall finishing in progress. MEP installation in progress, drywall cut at columns to be reinforced, reinforcing complete.
- 2nd Floor soffit framing demolished and ready to be re-installed with heavier gauge framing.
MEC / MESA Commons:
- 1st Floor overhead MEP installation in progress at time of site walk.
- 2nd Floor MEP rough-ins in progress.
MESA:
- 1st Floor ceiling tile stockpiled and awaiting installation, painting in progress, glass tile and wainscoting installation in progress. Floor polishing in progress.
- 2nd Floor ceiling grid and tile as well as painting in progress.
- 3rd Floor ceiling grid and tile as well as painting in progress.
View photos from the Skyview Campus Ground Breaking Ceremony!
Mechanical, Electrical, Plumbing and Fire Contractors Selected
- Mechanical: Air Comfort Service, Fort Collins
- Electrical: Merit Electric, Fort Collins
- Plumbing: Linds Plumbing & Heating, Fort Collins
- Fire: Western States Fire Protection, Denver
Progress Timeline:
| Design |
Construction |
Opening |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bond construction projects contact Whei Wong, 303.853.1049 |
District Upcoming Events
May 22- Board meeting, 6 p.m. Administration Building (591 E. 80th Ave.)
May 28- Memorial Day Holiday, all schools closed
May 30- 'Turn out the Lights' Pre demolition celebration at the Skyview Campus, 5:30 - 8 p.m. (8990 York St.)
|