Week endingApril 1, 2012
Work in Progress:
Clayton:
- 1st floor painting ongoing, tack board installation in progress.
- 2nd floor tile wainscoting installation ongoing, painting ongoing, tack board installation in progress.
Clayton / Academy Commons:
- 1st Drywall finishing in progress, stainless hood installation and duct welding in progress. Ceiling tile installation in progress in offices.
- 2nd floor commons painting in progress.
Academy:
- 1st floor Science equipment MEP work in progress, VCT stocked and awaiting installation..
- 2nd floor tile wainscoting complete, science equipment installation in progress, ceiling tile installation in progress, painting in progress, carpet delivered and awaiting installation.
View photos from the Skyview Campus Ground Breaking Ceremony!
Mechanical, Electrical, Plumbing and Fire Contractors Selected
- Mechanical: Air Comfort Service, Fort Collins
- Electrical: Merit Electric, Fort Collins
- Plumbing: Linds Plumbing & Heating, Fort Collins
- Fire: Western States Fire Protection, Denver
Progress Timeline:
| Design |
Construction |
Opening |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bond construction projects contact Whei Wong, 303.853.1049 |
District Upcoming Events
May 22- Board meeting, 6 p.m. Administration Building (591 E. 80th Ave.)
May 28- Memorial Day Holiday, all schools closed
May 30- 'Turn out the Lights' Pre demolition celebration at the Skyview Campus, 5:30 - 8 p.m. (8990 York St.)
|