• Phase 3: Planning and Design

Global Intermediate (4-8) Construction Updates

  • UPDATE - November 2018

    Posted by Andy Leapley on 11/7/2018
    • Design drawings are anticipated on Nov. 8 for review
    • Procurement of the abatement/demolition contractor for the existing building is in progress. Bids are due early November. 
    • Construction is currently scheduled to commence in March 2019 and completion is expected spring 2020. 
    Comments (-1)
  • UPDATE - Aug. 2018

    Posted by Blackboard Trainer on 8/1/2018

    Big Green reviewed their learning garden layout with the design team on Aug. 30. Collaboration between Big Green and Neenan resulted in some minor design changes. 

    RLH Engineering is handling the schematic designs for abatement, demolition, and the construction process. 

    Comments (-1)
  • UPDATE - July 2018

    Posted by Blackboard Trainer on 7/1/2018

    Project design is roughly halfway through schematic design; the floorplan is nearing its final shape, and Neenan will progress through Schematic Design documents in preparation for a set review in early August. Neenan will then issue their first construction estimate at the end of August. 

    NV5 has begun the procurement process for an Environmental Consultant to oversee the abatement process at the existing building. NV5 and the District will award the contract by July 6, pending some additional feedback from the Mapleton Executive Team.

    The current project milestones of construction commencement in March 2019 and completion in March 2020 still appear to be achievable. Although the project contingencies appear adequate at this time, the budget is built on the assumption of receiving a BEST grant in the fall. If State funding is not received, a budget reduction will be required.

    Comments (-1)

Global Intermediate Academy

  • PreK-3, 4-8, 9-12: three replacement schools located on the current site

    Architects: The Neenan Company
    Builders: The Neenan Company
    Design work: May 2018
    Construction begins: January 2019
    Projected cost for Global Intermediate (4-8 ): $16.7 million

    The District applied for two state BEST (Building Excellent Schools Today) grants this year to help pay for the PreK-3 and 4-8 schools but did not receive them. Mapleton plans to reapply for a BEST grant for the Global 4-8 school construction in 2018. Construction on the PreK-3 school will begin in August 2017.