• Phase 4: construction

Trailside Academy Construction Updates

  • UPDATE – February 1, 2019

    Posted by Andy Leapley on 2/1/2019
    • The building roofing is complete.
    • Interior wall framing is more than half complete.
    • Final furniture design was reviewed with Jordy Carter.
    • Design/build team is working n finishing touches such as ductwork encasements and cornerstone plaque placement. 
    • School expected to open in fall of 2019. 
    Comments (-1)
  • UPDATE – January 23, 2019

    Posted by Andy Leapley on 1/23/2019
    • Foundation concrete pours are complete.
    • Structural steel erection is complete, and steel stud framing is underway.
    • All roofing to be complete by January 18, 2019.
    • Classroom Data and Electrical mockup walked with MPS team.
    • No significant quality or schedule issues have been reported.
    Comments (-1)
  • UPDATE – December 14, 2018

    Posted by Andy Leapley on 12/14/2018

    interior design plans including furniture, fixtures and equipment choices are in process with Jordy Carter. Underground plumbing structural steel placement and gym roofing are complete. Steel stud framing and ground floor concrete pours are in process. No significant quality or schedule issues have been reported. The overall project budget of $20,550,000 has not changed this period.  Additional potential costs are also being tracked by NV5. Owner and Contractor Contingencies still appear adequate at this time. 

     

    Comments (-1)

Trailside Academy

  • A new PreK-8 school to be built in the Midtown neighborhood at 68th Avenue and Zuni Street

    Architect: RB+B
    Builders: Sampson Construction
    Design work: spring/summer 2017 
    Construction begins: Summer 2018
    Projected cost: $20.5 million