• Phase 3: Planning and Design

Explore Elementary Construction Updates

  • UPDATE – November 2018

    Posted by Andy Leapley on 11/7/2018
    • Project design development is complete and construction documents are in process with an anticipated completion date of December. 
    • Utility coordination with Xcel is ongoing Coordination of site improvements with the City of Thornton are making good progress. 
    • Construction is projected to start in early 2018 and school opening will be in 2020. 
    Comments (-1)
  • UPDATE – August 2018

    Posted by Blackboard Trainer on 8/1/2018

    On Friday, Sept. 14, staff from Explore Elementary will spend part of their Collaborative Day touring the new Adventure Elementary school building! The tour will be followed by a presentation of the proposed design of Explore’s new school building! Design concepts for Explore’s new school building are underway and should be finalized in the fall.

    Comments (-1)
  • UPDATE - July 2018

    Posted by Andy Leapley on 7/16/2018

    The Schematic Design package for Explore PK-8 was submitted on June 26 and is currently being reviewed by Mapleton and NV5. The general site plan and building floorplan has been established; however, modifications are still being made as design progresses and further District input is received. 
    The contract with the design-build team has been signed.  JHL is currently preparing preliminary pricing on the SD set for review on July 11 and July 18.  A committed construction schedule will also be presented in that time frame as well.  The construction schedule is dependent on discussions with the City of Thornton as to what construction activities will be allowed prior to finalization of an IGA or similar document between the City and the District. 
    The overall project budget has not changed, and Owner Contingency appear adequate at this time.
     

    Explore PreK-8 Design/Build team selected!

    The Board of Education and Mapleton administrators have selected the design/build team of JHL Constructors and Hord|Colpan|Macht (HCM) Architects to design the PreK-8 school building that will be constructed on the property at 104th Avenue and York Street. This building will be designed to reflect the heritage of Colorado farming and ranching in the area. Hint: The school may look like a barn! Planning and design will take place over the summer.

    Comments (-1)

Explore Elementary

  • Proposed Explore Elementary projects:

    • Relocate to a new school building and outdoor education center to be constructed on a portion of 25 acres near 104th Avenue and Steele Street
    • Program change from PreK-6 to PreK-8 to accommodate growth
    • Current Explore building would be remodeled and become a District-wide preschool center 


    Tentative timeline for new Explore PreK-8 building:

     

    Design: Aug. 2018 – March 2019
    Preliminary construction dates: March 2019 - Aug. 2020
    Proposed cost: $26 million  

    Tentative timeline for Explore Preschool Center (renovation of former Explore Elementary):

    Design: Jan. – June 2019
    Preliminary construction dates: June – Dec. 2019
    Proposed cost: $3.4 million