• Current Projects


Latest Updates

  • UPDATE – Dec. 5, 2019

    Posted by Andy Leapley on 12/5/2019
    • The playground equipment has been delivered to the site and crews from Bienstock Natural Playgrounds have started the installation.
    • Drywall installation is complete in all classrooms and most of the interior spaces. 
    • Paint is nearly complete within the gym walls and ceiling ductwork. 
    • On the side of the gymnasium, the trash encloser is beginning to take shape. 
    Comments (-1)
  • UPDATE – Nov. 21, 2019

    Posted by Andy Leapley on 11/21/2019
    • The final roof inspections are now complete!
    • The natural-themed playground equipment is now on-site and will be installed by crews for the next few weeks.
    • By the end of the week, the exterior seat boulders will all be placed.
    • Next week, the crews expect delivery of the metal wall panels for the entry silo.
    • Inside the building, crews are finishing up drywall installation throughout the school and are working on paint in many areas.
    • The gym brickwork is complete, meaning crews will soon work on painting the walls and ceiling ductwork.
    • Next week, tiling for the bathrooms will begin as well as blocking for the kitchen.
    Comments (-1)

Global Intermediate (4-8) Construction Updates

  • UPDATE – Nov. 1, 2019

    Posted by Andy Leapley on 11/1/2019
    • The erection of structural steel is now complete throughout the building. 
    • Crews have begun to pour slab-on-grade for the second floor and will soon begin on the classroom wing. 
    • To combat the weather, waterproof paneling now surrounds the building.  
    Comments (-1)
  • UPDATE – Oct. 17, 2019

    Posted by Andy Leapley on 10/17/2019
    •  Structural steel placement is wrapping up this week with only minor details remaining.
    • Braces for the classroom precast has been removed, allowing crews to begin backfilling.
    • Next week, crews will pour decking on the second floor.
    • Once the structural steel is complete, the crews will move inside for framing the classrooms and hallways!
    Comments (-1)
  • UPDATE – Oct. 11, 2019

    Posted by Andy Leapley on 10/11/2019
    • Precast concrete panel installation is complete. 
    • Structural steel placement is mostly complete throughout the structure. 
    • Installation of floor decking is in-process. 
    • Concrete slab on grade pours is scheduled for the beginning of October. 
    • Completion is expected for school to open the fall of 2020. 
    Comments (-1)

Latest Updates

  • UPDATE � Nov. 5, 2019

    Posted by Andy Leapley on 11/5/2019
    • The Welby Learning Park now has an entryway! Beginning on the northeast side of the park, visitors will walk through a large wooden archway that leads to 2.8 acres of Expeditionary learning opportunities.
    • Near the treehouse, crews have begun to place the steel bridge ramp leading up to the classroom space.
    • The learning park is scheduled to be completed by the end of November!
    Comments (-1)
  • UPDATE � Oct. 11, 2019

    Posted by Andy Leapley on 10/11/2019
    • Ordering and delivery of project-specific plantings has begun. Sod around the upper concrete pathway has been placed.
    • The structural steel bridge to the treehouse observation deck has been fabricated. Log placement for treehouse roof support and structural platform is in process.
    • The learning park is scheduled to be complete by November 2019. 
    Comments (-1)
  • UPDATE � Sept. 11, 2019

    Posted by Andy Leapley on 9/11/2019
    • Interpretive signage designs are being prepared for the District to review. Click here for an example of one of the signs! 
    • Site grading for concrete walkways is complete with concrete flatwork scheduled to begin shortly.
    • Learning park is scheduled to be complete by November 2019. 
    Comments (-1)