Project Timeline

  • Phase 4: Construction

     

Scope of Work

    • A new career training area supporting a broad range of content-based electives, including outdoor adventures, culinary arts, engineering, mathematics through art, forensic science, environmental studies, and others. 

     


Latest Updates

  • UPDATE – Aug. 9, 2019

    Posted by Andy Leapley on 8/9/2019
    • The CareerX space has been renamed The IDEA Lab, which stands for Innovation, Design, Entrepreneurship, and Academics. 
    • The function of the space will be career training, as well as opportunities for students to practice the principles of design thinking. 
    • Neenan is preparing new exterior signage design options for the District to review. 
    • Letter of Completion received from the State of Colorado on July 24, 2019. 
    Comments (-1)
  • UPDATE – July 17, 2019

    Posted by Andy Leapley on 7/17/2019
    • At the Broadway Campus, the IDEA Lab is nearing completion with the addition of signage and graphics to the interior.
    • Actual Neenan construction blueprints and renderings used to construct the building now serve as art on several walls!
    • Final inspections will occur throughout July, with the official opening the space scheduled for the fall.
    Comments (-1)

Project Details

  • 83.5% Completed


    Location:
    7350 N. Broadway, Denver, CO 80221

    Opens:
    Fall of 2019 

    Serves: 
    All students

    Website:  
    CareerX Department Page


    Project Budget: 
    $3 Million

    Architect:
    NV5

    Contractor:
    The Neenan Company

    Original Year Built:
    2019


      