Project Timeline

 

Phase 5: Complete!

 

Scope of Project

  • Construct new two-story PreK-8 school building with playground and field to be built on five acres near 68th Avenue and Zuni Street.

Latest Updates

UPDATE – Oct. 11, 2019

Posted by Andy Leapley on 10/11/2019

  • Punch list items are complete!
  • Crosswalk and ADA ramp revisions are under discussion with Adams County. 

UPDATE – Sept. 11, 2019

Posted by Andy Leapley on 9/11/2019

  • Punch list items are essentially complete. 
  • Site landscaping is 90% complete.
  • The playgrounds are complete. 
  • Trailside held their Ribbon Cutting Ceremony on Thursday, Aug. 15 with the first day of school for students on Monday, Aug. 19, 2019.

Project Details

100% Complete!

Location:
2300 W. 67th Pl., Denver, 80221

Opened 
August 19, 2019

Serves: 
Grades PreK-8

Website:  
Trailside Academy School Website

Project Budget: 
$20.5 Million

Architect: 
RB+B

Contractor: 
Sampson Construction

Original Year Built:
2019