Global Intermediate (4-8) Construction Updates

  • UPDATE – Jan. 17, 2020

    Posted by Andy Leapley on 1/17/2020
    • Global Intermediate Academy’s library is now fully enclosed by the Kalwall translucent wall panels! The library will allow natural daylight to flow through the area with glare-free usable light during school hours and a unique glowing effect at night.
    • For the next few weeks, crews will focus on the exterior primer, stonework, and installation of the last precast windows.
    • Inside the school, steel framing is complete on the first floor and close to wrapping up the second floor.
    • Drywall has started enclosing the first floor classrooms and hallways, and will soon move upstairs.
    Comments (-1)
  • UPDATE – Jan. 9, 2020

    Posted by Andy Leapley on 1/9/2020
    • The exterior is nearly "closed-in" with exterior finish materials underway, including brick and metal paneling. 
    • The upper roof is complete; the lower roof is underway.
    • The interior wall framing is complete on the first floor allowing crews to apply drywall. 
    • Completion is expected for school to open the fall of 2020.