UPDATE - July 2018

Posted by Blackboard Trainer on 7/1/2018

Construction at Global PK-3 is progressing rapidly toward it’s expected TCO date of Aug. 10. 
  • Interior finishes are nearing completion throughout the building, and playground spaces are beginning to take shape.
  • Owner punch walks have been scheduled for the week of July 16.
  • Interior signage is scheduled for installation in mid-July, and FF&E installation will take place Aug. 6 through Aug. 10. At this time, progress appears to be on track to complete for the on-time return of teachers and students.
  • Neenan has issued Owner Change Orders #4 and #5 for scope changes including additional site improvements, finish changes and project savings. The overall budget of $18,001,401 is intact, with approximately $532K in unallocated funds.