UPDATE – Oct. 11, 2019

Posted by Andy Leapley on 10/11/2019

  • Precast concrete panel installation is complete. 
  • Structural steel placement is mostly complete throughout the structure. 
  • Installation of floor decking is in-process. 
  • Concrete slab on grade pours is scheduled for the beginning of October. 
  • Completion is expected for school to open the fall of 2020.