UPDATE – Feb. 28, 2020

Posted by Andy Leapley on 2/28/2020

  • The exterior gravel for the playground will be placed once the weather allows. 
  • In the next few weeks, the trailer will move to another site to make room for crews to tend to the landscape and seed the ground. 
  • the preschool shade structure will be installed in early March. 
  • Next week, the acoustic panels will be delivered for paint and installation in the gym. This will allow better sound in the large space. 
  • Pads for the gym walls will also be installed. 
  • The gym projector screen will be installed on March 11. 
  • The light poles are at the school and will be installed soon. 
  • Floor polishing is complete in the classroom commons and will move on to the grand hall and western classrooms next.