UPDATE – March 5, 2020

Posted by Andy Leapley on 3/5/2020

  • At the Mapleton Arts Center (MAC), crews are finished with the underground electrical work and will wrap up plumbing by the end of the month.
  • The large, two-story dirt pile is now down to mere feet and almost completely removed from the site.
  • Crews will soon begin pouring the concrete slab for the foundation and the building is expected to go vertical at the beginning of April! 
  • The MAC will serve students district-wide and is scheduled to be open in 2021.